In January 2026, 5.8% of German manufacturers reported material shortages. By April it was 13.8%, in June 17.2%, in September 14.6%. Among manufacturers of data processing equipment and electronic and optical products, the share rose from 37.8% to 41.5% between September and October alone, according to the ifo Institute's surveys. Supply conditions shift noticeably within a few weeks. The executive meeting in sales and operations planning (S&OP), by contrast, takes place only once a month in most companies.
This article explains what sales and operations planning is, how the process works and what it delivers. It also shows where a monthly cadence hits its limit. numi's view: S&OP should be built bottom-up. Whether an item is available next week, or whether a production line stops, is decided in day-to-day operations, not in the monthly meeting. If you make the right decision per SKU every day, the basis for the weekly alignment and the monthly S&OP is already in place.
Key takeaways
- S&OP is a monthly management process that brings demand, production, procurement, inventory and finance into one agreed plan. It plans at product family level and over many months.
- A monthly cadence is too slow for disruptions. Around 30 days pass between two executive meetings. Delivery delays and demand spikes often hit individual items within days or a few weeks.
- Bottom-up closes the gap. Daily improvement recommendations per SKU prevent stockouts, excess inventory and production disruptions. Rolled up, they also provide the basis for easy weekly and monthly decisions.
What is sales and operations planning (S&OP)?
Sales and operations planning (S&OP) is a cross-functional management process that balances a company's demand and supply in one shared plan. Sales, marketing, production, purchasing, logistics and finance typically align their demand, production, procurement and inventory plans once a month. The result is a rolling plan at product family level, approved by senior management.
The approach emerged in the early 1980s as a process for balancing supply and demand. The consultancy Oliver Wight describes it as the forerunner of today's integrated business planning (IBP). SAP describes the process as typically monthly, producing a rolling plan that extends 18 to 36 months.
Three traits separate S&OP from operational planning:
- Aggregated: It plans product families, plants and regions, not individual items and locations.
- Mid-term: It looks months to years ahead, while capacity, staffing and budget can still be changed.
- Decision-oriented: The output is not a report but an approved plan with clear decisions on trade-offs.
How does the S&OP process work? The 5 steps
Labels vary by company and textbook. At its core, the S&OP process consists of five steps that repeat every month.

| Step | Key question | Output | Typical timing |
|---|---|---|---|
| 1. Data and portfolio review | What happened, and what is changing in the range? | Cleansed actuals, launches, phase-outs | Week 1 |
| 2. Demand review | What do we expect to sell? | Consensus demand plan, unconstrained | Week 2 |
| 3. Supply review | Can we deliver it? | Check against capacity, materials and inventory | Week 3 |
| 4. Pre-S&OP | Where are the gaps, and what are the options? | Scenarios and reconciliation with the financial plan | Week 3 to 4 |
| 5. Executive S&OP | Which option do we choose? | Approved plan, documented decisions | Week 4 |
One detail matters for understanding the limits: in this schedule, the data from step 1 is already up to three weeks old by the time the executive meeting happens. Another 30 days or so pass before the next one.
What are the benefits of sales and operations planning?
S&OP done well pays off. According to a Gartner survey, organizations with well-designed S&OP processes are 1.2 times more likely to outperform competitors on metrics such as OTIF, cost or inventory (Supply Chain Management Review, April 2025).
The main effects:
- One plan instead of many: Sales, production and finance work from the same assumptions.
- Early capacity decisions: Shift models, outsourcing or investments are decided while they can still be implemented.
- Visible trade-offs: Service, inventory and cost are weighed against each other deliberately.
So abolishing S&OP is not the answer. The real question is which decisions belong in this process and which do not.
Why is the monthly S&OP cycle too slow for disruptions?
S&OP was built for decisions with weeks or months of lead time. For disruptions in daily operations, the process has four structural weaknesses.
1. The cadence gap: 30 days is longer than many items' days of cover
If a disruption hits the day after the executive meeting, it is back on the agenda roughly four weeks later. If an item has only two to three weeks of cover, the stockout has already happened before anyone in the meeting discusses it.
2. Aggregation: stockouts happen per item, not per product family
A product family can look balanced in the plan while individual items are missing and others sit in excess. But the customer orders a specific item, and production needs a specific component. S&OP does not see that level.
3. Static parameters: the ERP calculates with yesterday's values
Safety stocks, reorder points and replenishment lead times often stay unchanged between cycles. If a supplier's lead time grows from 14 to 18 days, the system keeps ordering as if nothing had changed.
4. Meeting capacity: a committee cannot review a thousand exceptions
An S&OP meeting can decide a handful of trade-offs. With a large item portfolio, however, daily operations produce many item-level signals every day: moved delivery dates, demand spikes, overdue purchase orders. If these topics end up in S&OP anyway, they crowd out the mid-term view. According to Gartner, 42% of supply chain organizations struggle to lift the focus of S&OP beyond short-term objectives (Supply Chain Management Review, April 2025).
Research shows the scale as well: in 2020, the McKinsey Global Institute estimated that companies can expect a supply chain disruption lasting a month or longer every 3.7 years on average. Smaller disruptions are routine, and they unfold much faster than a monthly cycle.
Worked example: how much reaction time is left between two S&OP meetings?
A simple example makes the gap visible. Starting position on the day of the S&OP meeting (day 0):
- Inventory: 1,000 units
- Planned demand: 40 units per day
- Open purchase order: 800 units, due on day 15
- Next S&OP meeting: day 30
The assumption: until then, the item runs on the parameters from the last planning round, and nobody actively reviews it while it is not on any agenda. In many companies with thousands of items to manage, that is the normal case.
On day 5, two signals arrive. The supplier pushes the order back by 12 days to day 27. At the same time, demand rises by 25% to 50 units per day.
Inventory on day 5 = 1,000 - 5 × 40 = 800 units
Days of cover = 800 ÷ 50 = 16 days (stock hits zero on day 21)
Stockout without reaction = day 21 to day 27 = 6 days × 50 = 300 units
Assume a backup supplier can deliver within 10 days. Then:
Reaction window = days of cover - lead time of the countermeasure
Reaction window = 16 - 10 = 6 days
The backup order must therefore be placed by day 11 at the latest.
| Cadence | When is the signal reviewed at the latest? | Result in the example |
|---|---|---|
| Monthly only (S&OP cycle) | Day 30, which is 25 days after the signal | The stockout has already happened: 6 days, 300 units |
| Weekly (S&OE) | Up to 7 days after the signal, day 12 at the latest | One day too late in the worst case |
| Daily | Day 6 | A backup quantity of 400 units arrives on day 16, when 250 units are still in stock. No stockout |

The same logic applies in the other direction. If demand drops on day 5, the planned order still goes out under a monthly cadence and creates excess inventory. A daily review recommends postponing or reducing the order.
Bottom-up S&OP: which cadence for which decision?
The answer to the cadence gap is not to hold the S&OP meeting more often. It makes more sense to assign each decision to the cadence that fits it and to build the process bottom-up: the daily decision per SKU is the base, and the week and the month build on it.

1. Daily: decisions per SKU
- How it works: Software checks inventory, demand, open orders and delivery dates per SKU every day and ranks concrete actions by impact.
- When it fits: Ordering, expediting, postponing, cancelling, parameter changes and supplier escalation.
- Delivers: A short, prioritized list instead of a meeting. Plus data that is current every day and can be rolled up for the week and the month.
- Risk: It needs clean master data and targets such as service levels and inventory budgets. Without targets, every recommendation optimizes toward nothing.
2. Weekly: S&OE for the exceptions
According to ASCM, sales and operations execution (S&OE) is a weekly or more frequent planning process that addresses execution-level supply and demand imbalances.
- How it works: Planning, purchasing, sales and production discuss the cases that cannot be solved at SKU level alone.
- When it fits: Allocating shortages, prioritizing orders and sequencing production over the next few weeks.
- Delivers: Agreed countermeasures, plus escalation to S&OP when the frame no longer holds.
- Risk: Without the daily groundwork, the meeting only covers the most visible exceptions across thousands of items, and a delay of up to 7 days can be too long.
3. Monthly: S&OP for frame and targets
- How it works: Five steps per month, ending in an approved plan at product family level.
- When it fits: Capacity, budget, portfolio and trade-offs with months of lead time.
- Delivers: One shared plan and guardrails such as service levels and inventory targets, which flow back into daily control.
- Risk: Without current numbers from below, the committee decides on outdated, aggregated data.
Why does bottom-up make weekly and monthly decisions easier?
- Current numbers instead of data collection: Inventory, forecasts and open orders are maintained every day. The data review at the start of the cycle gets shorter.
- Fewer topics in the meeting: Operational one-off cases are already solved. Only the trade-offs that cannot be resolved per SKU reach the table, such as missing capacity.
- One set of numbers: The monthly view per product family is the sum of the SKU decisions, not a separately maintained set of figures.
Bottom-up does not mean that targets come from below. Service levels, inventory budgets and capacity limits are still set in S&OP. Eric Wilson of the Institute of Business Forecasting (IBF) points out that S&OE complements S&OP rather than replacing it (demand-planning.com, November 2026). We agree, and we go one step further: the base has to be built daily and per SKU. Then the weekly and monthly meetings only handle the exceptions.
Decision matrix: which decision belongs in which cadence?
| Decision | Horizon | Level | Suitable cadence |
|---|---|---|---|
| Capacity, shift models, investments | Months to years | Plant, product family | Monthly (S&OP) |
| Reconciliation with budget and revenue plan | Quarter to year | Company | Monthly (S&OP) |
| Promotions and new product launches | 1 to 6 months | Product family, item | Monthly, fine-tuned weekly |
| Allocating shortages, prioritizing orders | 1 to 12 weeks | Order, line | Weekly (S&OE) |
| Safety stock, reorder point, order quantity | Days to weeks | Item, location | Daily |
| Placing, expediting, postponing or cancelling orders | Days | PO line | Daily |
| Escalating suppliers on late deliveries | Days | PO line | Daily |
Industry examples: what does S&OP settle, and what needs a daily decision?
| Industry | Typical disruption | Settled monthly in S&OP | Needs a daily decision |
|---|---|---|---|
| Retail and e-commerce | A promotion outperforms the plan | Promotion calendar, budget, warehouse capacity | Reorders per item, transfers between locations |
| Wholesale | A supplier extends its lead time | Supplier strategy, target stock per category | Adjusting reorder points, pulling orders forward |
| Industry and manufacturing | A component arrives late | Capacity plan, make-or-buy | Identifying affected production and customer orders, escalating suppliers |
| Aftersales and spare parts | Intermittent demand jumps | Service level targets per part class | Safety stock per part, rush orders for critical parts |
How numi does S&OP bottom-up
numi starts with the individual SKU and works daily. The software translates targets such as service level and inventory level into prioritized decisions per SKU. The same data can be rolled up for the weekly alignment and the monthly S&OP.
- Daily inventory recommendations: numi inventory optimization recalculates safety stocks, reorder points and order quantities every day and provides prioritized recommendations for parameter changes. You can simulate the impact before values are transferred to the ERP.
- Order proposals based on the current situation: numi replenishment combines inventory, open purchase orders, customer orders, reserved stock, AI forecasts and lead-time predictions into concrete order proposals.
- Up-to-date forecasts: numi forecasting updates demand forecasts automatically and raises alerts when demand shifts.
- Early detection of missing parts: In the solution for industry and manufacturing, numi checks inventory, purchase orders and demand across multi-level bills of materials and shows which production and customer orders depend on a delayed part.
- Automating routine work: numi Agents monitor risks, notify suppliers about critical delays and prepare approvals.
- Roll-up for week and month: In numi, forecasts can be adjusted across planning hierarchies, aggregation levels and time horizons. Inventory values can be analyzed by location, product group and ABC class. Management reports can be created through numi MCP with ChatGPT, Microsoft Copilot or Claude.
With numi, customers achieve up to 30% less excess inventory and up to 20% fewer stockouts.
Further reading: Delivery date monitoring: detect delivery delays early and Demand planning models, process and KPIs.
Conclusion
Sales and operations planning is the right process for decisions with lead time: capacity, budget, portfolio. For demand and supply disruptions, a monthly cadence is too slow. If you do not steer between two meetings, you learn about stockouts, excess inventory and production disruptions only after they have happened.
The practical consequence: build S&OP bottom-up. The base is a daily, software-supported check per SKU that recommends concrete improvements and ranks them by impact. The weekly and monthly view emerges from those decisions. The meeting then decides on targets and trade-offs, not on individual cases, which makes it shorter and easier.
Book an intro call – we will show you what daily recommendations could look like in your planning.
Sources
- ifo Institute: Material Shortages in German Manufacturing Rise Again, press release, October 12, 2026
- ifo Institute: Surge in Material Shortage in German Manufacturing, April 30, 2026
- ifo Institute: Material Shortages in German Manufacturing Worsen, July 7, 2026
- Reuters via onvista: Ifo: Materialengpässe in der Elektroindustrie verschärfen sich (German), November 13, 2026
- SAP: What is sales and operations planning (S&OP)?, accessed November 23, 2026
- Oliver Wight: Integrated Business Planning, accessed November 23, 2026
- Sarah Gilchrist (Gartner): 3 transformative trends impacting S&OP strategies, Supply Chain Management Review, April 18, 2025
- ASCM Insights: Direct Your Supply Chain Plans to Execution, July 20, 2022
- Eric Wilson (IBF): Is It Time for S&OP To Step into the Future?, demand-planning.com, November 8, 2026
- McKinsey Global Institute: Risk, resilience, and rebalancing in global value chains, August 6, 2020